Health |
Resolved |
This is shell only at this time, no review from health needed until interior fit up |
Inspections |
Resolved |
Will this permit be for only a shell building with no insulation?(7/25 Insulated shell) |
Inspections |
Resolved |
Will you be using the existing foundation for this structure?(7/25 Yes) |
Inspections |
Resolved |
Sheet A-300 detail#2 shows no continuous insulation? IECC 2018 Table C402.1.3. |
Inspections |
Resolved |
Sheet A-300 detail#10, the foundation insulation does not go to the top of the floor slab. 2018 IECC section C402.2.4. |
Inspections |
Resolved |
Sheet A-300 details 2 and 3, will the glazing comply with section 2406.4.2? |
Inspections |
Resolved |
Will there be any outdoor seating provided for this building? (Fixture counts) |
Inspections |
Resolved |
It is the responsibility of the permit holder to verify the existence of any covenants or easements existing on this property. |
Inspections |
Resolved |
If changes occur to the plans or specifications as a result of this review or for any other reason, revisions shall be issued as required and forwarded to this office. |
Inspections |
Resolved |
A copy of this review, all responses, plans or specifications changes, or any other subsequent information pertaining to this project shall be provided to the contractor for his information. |
Inspections |
Resolved |
This building and its associated site shall be accessible per IBC Section 1009, Chapter 11 and ANSI. |
Inspections |
Resolved |
Complete and return the following form: ADAAG Conformance Statement (return copy, send original to address shown on the form) |
Inspections |
Resolved |
Sheet S002, Special inspections and reporting (if required) shall be provided on this project per IBC Sections 1704 and 1705. The permit applicant shall submit a statement of special inspections as required by IBC Sections 1704 and 1705. A copy of a summary is attached for your use. Please provide a list of special inspectors and their qualifications. Special inspector shall provide this office with a final report documenting required special inspections and correction of any discrepancies noted in the inspections as required by IBC Section 1704.2.4. A certificate of occupancy may not be issued for this project until the final report is received by this office. |
Inspections |
Resolved |
Provide information on compliance with the International Energy Conservation Code 2018. Comply with IECC Sections 401-405 or 407 as required. Computer-generated documentation (e.g. ComCheck) will be allowed to indicate total building performance as per IECC Section 407.6. Your summary must include building envelope, mechanical systems, water heating, interior lighting and electrical power systems. |
Inspections |
Open |
Commissioning of new Buildings. Per the requirements of the International Energy Conservation Code, section C408, new buildings with 480 kBtu/h Cooling and 600 kBtu Heating capacities are required to undergo commissioning. It is designer’s responsibility to plan and apply all required commissioning procedures and fulfill the required documentation as prescribed in section C408. The registered design professional is required to provide copy of Commissioning Report to the Building’s owner within 90 days from date of receipt of Certificate of Occupancy (IECC sections C408.2.5 and C408.3.2). Statement from the registered design professional stating that commissioning report is provided to owner shall be submitted to our office. |
Inspections |
Resolved |
There have been no plans submitted for the systems for this project. These systems (Plumbing, Mechanical and Electrical) shall comply with all the requirements of the City of Fargo and its adopted codes. These plans will be allowed as deferred submittals per IBC Section 107.3.4.1. Please review and approve these plans for compliance and forward them to this office for our review. No work can start on these systems until approved. |
Inspections |
Resolved |
There is not approval for the fixture count as per table 2902.1 since this building is a shell building only. |
Inspections |
Resolved |
Sheet C1, Please provide me with separated values for the building and the parking lot. These pieces will be permitted individually. You can also apply for the parking lot permit on-line and adjust the value for the building permit as needed, then resubmit. |