Investigation / Walk-Through |
2/24/2021 2:14:19 PM |
Passed |
|
Investigation / Walk-Through |
3/10/2021 2:46:23 PM |
Passed |
|
Consultation |
1/25/2021 11:18:05 AM |
Passed |
|
Consultation |
3/9/2021 11:00:00 AM |
Passed |
|
Grounding Electrode |
12/21/2020 10:49:41 AM |
Passed |
|
Footing |
12/21/2020 9:15:00 AM |
Passed |
|
Foundation |
1/4/2021 10:00:00 AM |
Passed |
|
Slab |
2/25/2021 8:00:00 AM |
Passed |
|
Rough Fire |
5/26/2021 1:15:00 PM |
Failed |
|
Framing |
1/25/2021 9:00:00 AM |
Passed |
|
Framing |
3/10/2021 3:00:00 PM |
Passed |
|
Framing |
3/11/2021 1:00:00 PM |
Passed |
|
Certificate of Occupancy |
6/7/2021 12:00:00 PM |
Passed |
|
Final Building |
5/25/2021 2:15:00 PM |
Failed |
|
Final Building |
6/1/2021 3:00:00 PM |
Failed |
|
Final Building |
6/7/2021 8:45:00 AM |
Passed |
|
Final Building |
5/25/2021 2:30:00 PM |
Failed |
|
Final Building |
7/21/2021 2:30:00 PM |
Failed |
|
Temporary Electrical Service |
11/17/2020 10:00:00 AM |
Passed |
|
Above Ceiling Electrical |
5/5/2021 2:15:00 PM |
Failed |
- Cnt use TC cable in the manner it was used. Must remove from ceiling.
|
Above Ceiling Electrical |
5/7/2021 10:15:00 AM |
Passed |
- Cnt use TC cable in the manner it was used. Must remove from ceiling.
|
Rough Electrical |
3/10/2021 11:30:00 AM |
Passed |
|
Rough Electrical |
3/17/2021 12:45:00 PM |
Passed |
|
Electrical Service |
4/26/2021 9:30:00 AM |
Passed |
|
Final Electrical |
5/28/2021 10:35:00 AM |
Failed |
- 1. Need panel schedules and source labels
- 2. Need face plates for receptacles.
- 3.Baseboard heater not powered. Wires hanging out.
- 4. Need dated fault current label for RTU
- 5. Need to Ground RTU disconnect.
- 6. 12×12 j-box at RTU has 2 ground wires under 1 lug. Separate into individual lugs.
- 7 12×12 j-box at mini split units has to many wires under 1 lug. Must install ground bar in this j-box and separate wires under individual terminations.
- 8. Bonding jumper to light pole ground rods must be minimum #8 from rod to pole and must ground pole at hand hole location.
|
Final Electrical |
6/2/2021 2:00:00 PM |
Passed |
- 1. Need panel schedules and source labels
- 2. Need face plates for receptacles.
- 3.Baseboard heater not powered. Wires hanging out.
- 4. Need dated fault current label for RTU
- 5. Need to Ground RTU disconnect.
- 6. 12×12 j-box at RTU has 2 ground wires under 1 lug. Separate into individual lugs.
- 7 12×12 j-box at mini split units has to many wires under 1 lug. Must install ground bar in this j-box and separate wires under individual terminations.
- 8. Bonding jumper to light pole ground rods must be minimum #8 from rod to pole and must ground pole at hand hole location.
- 1. Need panel schedules and source labels
- 2. Need face plates for receptacles.
- 3.Baseboard heater not powered. Wires hanging out.
- 4. Need dated fault current label for RTU
- 5. Need to Ground RTU disconnect.
- 6. 12×12 j-box at RTU has 2 ground wires under 1 lug. Separate into individual lugs.
- 7 12×12 j-box at mini split units has to many wires under 1 lug. Must install ground bar in this j-box and separate wires under individual terminations.
- 8. Bonding jumper to light pole ground rods must be minimum #8 from rod to pole and must ground pole at hand hole location.
|
Rough Fire Alarm |
6/1/2021 2:28:12 PM |
Passed |
|
Final Fire Alarm |
6/1/2021 2:27:45 PM |
Passed |
|